on 06-17-2009 1:26 PM
Hello All,
Is there any facility in PS where we can issue " Interm Payment Certificate" after say completion of 15% of work, I am issuing payment certificate for 15% amount.
Thanks,
Hari
Hi
You can try this in CJ20N
Select the external activity(Service / Contract) select the menu path Edit--> Activity --> Invoicing Plan
Here you can declare the percentage for the invoice.
Hope this will helps you
Thanks
S.Murali