R/3 -APO planned order date mismatch

Former Member
0 Kudos

Hi all

I have created a planned order in R/3 on 20.7.2009 and cif to APO but in APO (Product view/snp planning book) it appears on 21.07.2009.

I checked all GR processing time in BOM component as well as header material is ZERO.Also run CCR there is no error in CCR.

please give some solution

thanks & regards

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Sanjay,

Please check the following & confirm back.

1) Check SAP note 423626, 394113

2) Check your settings in transaction /SAPAPO/CP3

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Sanjay,

This is a everywhere found issue. .

Actually the main issue is, the calender and time settings in R/3 are different than that in APO and hence you will many a times find the same inconsistency.

Till now, i havent found a solution on this.

But i hope i have cleared your doubt. .

Please let mw know your comments on the same.

Regards,

Prasad.

Former Member
0 Kudos

Hi Sanjay,

Check the time series data in APO. Probably this is calendar error.

Regards,

Santosh