Dear Gurus,

Is it possible to club the diiferent deliveris in to one inspection lot.

For example, presently system creates 1 inspection lot per delivery.

If user wants next delivery also linked to previous lot and no need of getting a new lot for the current delivery.

Is it possible.

Pls advice.

Siva

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

U can also use Dynamic Modification Rule in Quality view of material.

If DMR is 1 inspect 3 skip, only first inspection lot will come to inspection. 3 lots after that will be skipped after certain period.

Former Member
0 Kudos

Hi Siva,

You can use the Control Inspection lot field within the inspection lot default values to determine when the system must create the inspection lot. Eg for each material document or each purchase order etc

Quality Management -> Quality Inspection -> Inspection lot creation -> Define default values for Inspection Type

Regards,

Roderick

Former Member
0 Kudos

Hi

If you done the result recording and UD for the quality lot , they lot get closed.It is not possible to add some more quantity in the same lot.In general each delivery will have their own inspection lot.

Thanks