TCODE - E2DY

Former Member
0 Kudos

Hello,

I wonder if there is some limit according to this Transaction,when I want to CHANGE The Scheduled MR DATE ?

I will be able to change the Date when if Today is 16/6/09 and I can see that I can't read today,I will be able to make the change?

I saw that if I performed el01 to an Installation to a SMRD of 16/6, I can't change it anymore!

Someone know it for sure?

Thanx,

Mike.

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Hi Michael

It is better to use E1DY and generate new dates from now on insted of changing the old one.

ShoshF

View solution in original post

2 REPLIES 2

Former Member
0 Kudos

Hi Michael

It is better to use E1DY and generate new dates from now on insted of changing the old one.

ShoshF

Former Member
0 Kudos

Hi Michael,

Please follow the below steps to change the SMRD in the E2dy-transaction.

1.Enter the billing year for which the planning to be carried out.

2.Enter factory calendar.

3.Click the Dynamic Portion only checkbox.

4.Click execute (F8) to list all portion for the complete year.

5.To reschedule the Meter reading/Billing date, double-click on the date on the calendar list.

6.A pop up window will appear , enter the NEW date on the Tgt date field and click execute (F8).

7.Once all the date are scheduled, click to save new changed schedule

8.A successful message will be displayed at the bottom of the screen indicating that the <Database changes has been made>.

I hope the above steps may help.

Warm Regards,

Sasi Kumar.D