Customer Requested Delivery Date In the Past

Former Member
0 Kudos

Hi All.

During order creation if the Customer's Requested Delivery Date is in the past, then what will happen?

How to set the system response?

Thanks in Advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

While entering the sales, if you maintain the customer's requested date as in the past then system would give you a warning message and you can proceed. When you enter the material it would not be possible to deliver the goods as per the customer's requested date and hence system would carry out the forward scheduling and propose the next possible date when the delivery can be made to the customer. This would ensure you have more than one schedules line for the line item.