Can any one explain the Budget utilization in SAP-PS.

Bekele

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Bekele,

Budget utilization againt a WBSE is based on the commitments (PRs and POs) plus actual costs booked against that WBSE.