Dear All
How to add the Service Activity in network and After that what r the process we had to do link entry of service master list
regards
raj
HI raj,
in CN22, go to tab 'Total', select option 'service' for a new line, input the activity description. Then you should get the service screen.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Drag and Drop Service activity/External Activity to the network header
Enter a meaningful description,vendor,contract number and organisational details
which will take you into service spec overview screen where you can enter the your own service
or a predefined service activity no (AC01 -mm module) which followed by req quantity,unit price,cost element.Enter overall limit if you expect any unforseen cost for all line times,overfullfilment tolerance gives expected overlimit in terms of qunatity.
To Diplay the service once after saving just click on the service button in the external activity
Regards
Anish PV
thank to every one
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Drag and drop the service activity on to the WBS element in the CJ20N and enter the purchase group, material group, cost element ( if all these are not maitained in the network profile). This will take you to the next screen where in the service master can be entered.
Hope this will help you
Regards
K Ramaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.