Hi All SAP Gurus,
In our company we are using service activity only, because we plan value on service basis.
Problem is that- when I am executing S_ALR_87013532 & S_ALR_87013533 report system only shows service consumption on each activity level. Material consupmtion can not display. But on site they are doing material issue on activity level by 281 Q movement type.
Please suggest.
Thanks in advance and Regards,
Pravin
Pravin,
If I understand your question correctly, the material cost is not being shown at the activity level but at the WBS element level ( this I am assuming pls correct me if I am wrong here) when goods is issued ( 281 Q). If this exactly is the problem then pls check if you are using non-valuated project stock, because the project specific material issue (281Q ) will not be a valuated good movement and WBS element is the actual cost object. Hence the the cost will be shown at the WBS element leve instead of at the network activity level.
Do revert if my understanding of your question is right or for any further clarifications.
Regards
K Ramaiah
Edited by: Kodanda Ramaiah on Jun 15, 2009 2:31 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Still you can find the value from the report.Double click on the business transaction on the left side after executing the report ;the list will display the material purchase orders and purcahse requisitions e.t.c.Hope this will clarify the requirement.It seems that you are carrying out non stock procurement(N-item category).
regards
Anish PV
You can see cost for an indiviual activity by making customizing setting in transaction OPUV
in network type parameter screen, "Actvty Acct Asgn" check box must be ticked, to see cost at activity level.
Indicator:Account assignment on activity level
Indicator which specifies that the account assignment is to be carried out at activity level.
If you do not set this indicator, the account assignment is carried out at Network header level.
after doing this setting run CJEN and then check the your reports. see if problenm is resolve or not ?
Hi Praveen,
Are you using Non-Valuated Project Stock ??
If your answer is "Yes" , System shows actual cost of material issued to service activity at WBS Element Level Only, not on Service Activity Level. This is Standard SAP Functionality.
If you are using Valuated Project Stock, System shows you the actual cost of material consumption against service activity.
Hope this clears you !!
Regards,
Hari.
Hi,
Please check the cost Rel. tick in Material component on Purch. Data tab in Project Structure ( CJ20N).
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi praveen,
Check the Component Option is selected or not in Database profile you are using in T-Code - OPTX.
Regards,
Hari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.