CJ88 : Automatic posting in AUC

pradeep_mahamuni
Contributor
0 Kudos

While doing automatic settlement to AUC assigned values changes for the WBS cost amount.

eg. WBS actual cost is 10,000 so before doing settlement Assigned value is 10,000 in CJ31

after running CJ88 assigned value in CJ31 changes to 20,000.

also in report S_ALR_...3558 for budget / actual in actual cloumn values changes to 20,000.

can anybody rell me why it is happening ? any config related setting is there ?

regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Pradeep,

Run CJEN once and check the report now !!

Regards,

Hari.

pradeep_mahamuni
Contributor
0 Kudos

I tried all this thisngs,

Ran CJEN. CJBN but still problenm is as it is.

Mrinal_K_Roy
Active Contributor
0 Kudos

Do you also settle subordinate WBS .if s , then u need to exempt cost element from lower level WBS . Refer oss note 159850.

Regards,

Mrinal

pradeep_mahamuni
Contributor
0 Kudos

i am not settlting to subordinate WBS. I doing settlement thorigh CJ88 by selecting automatic posting, it will settle the WBS against already created AUC.

settlement cost element is maintained in budget exempt list.