In PM maintenance order if i have total 6 technical objects assigned in object tab then the cost tab will display the total cost of the order . I want to know the cost for each technical object .
I know there is some User exit for this but not sure .
Can any one please guide me on this
hi
i think you can use user exit IWO10027 User exit: Generate user-defined settlement rule
to determine the settlement rule for the technical object entered in the object list .and get settled to the respective cost center ,which will reflect in the cost analysis report
regards
thyagarajan