Object level costing in PM order

Former Member
0 Kudos

Hi Experts ,

In PM maintenance order if i have total 6 technical objects assigned in object tab then the cost tab will display the total cost of the order . I want to know the cost for each technical object .

I know there is some User exit for this but not sure .

Can any one please guide me on this

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

i think you can use user exit IWO10027 User exit: Generate user-defined settlement rule

to determine the settlement rule for the technical object entered in the object list .and get settled to the respective cost center ,which will reflect in the cost analysis report

regards

thyagarajan