on 06-12-2009 7:37 AM
Dear All
when i am going for the close of the project i am getting the this type of error
Error when processing asset under construction (AuC) for WBS element
A-AKERI-09-01.01
Message no. CJ824
Please guide me to solve this error
regards
raj
Hi
Do the AUC settlement and Project settlement then try to close the project.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raj,
Before closing the project, All Aucs must fully settled to Asset. Check the Auc status and then close the project accordingly.
Check the Auc of WBSE A-AKERI-09-01.01.
regards,
Hari.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Refer SAP Note:924944.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.