on 06-11-2009 10:48 AM
Hi all,
Small question, i ahve some pricing conditions that use the Serives Rendered date and others that use the Pricing Date from an order, how is the condition decided on what date it uses?
Hope i have expplained this ok, if not and you need more info let me know.
Regards
Steve
Hi
There is a difference between Service Rendered Data and Pricing Date.
Normally Freight Conditions are maintained on Service Rendered Date so the freight will be picked on the basis of date on which the Actual Delivery done, whereas Pricing date is used for other conditions so that price will be based on the date on which the document created and the Pricing Date maintained in that.
In the same way there is a Billing Date which came in Invoice so price will be based on the date of Invoicing.
If you maintain the record in VK11 and test a cycle you will be able to find the difference easily.
Regards
Amitesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Create the condition record for those condition types which are based on the service rendered date using VK11 T.Code.
In this maintain the validity period.
So if your service rendered date is in that limit then it will pick up that price.
You can create scales also using the same T.Code.
Reagrds,
Krishna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.