on 06-10-2009 11:55 PM
All,
We are trying to create inspection plans using the bapi BAPI_INSPECTIONPLAN_CREATE. However we are unable to create it as we are getting an error for the bapi which tells us :
"This inspection point completion is not possible for task list type Q"
we are giving the following fields :
PROFILE
VALID FROM
TL_USAGE
task list desc
PLANT
TL_STATUS
from lot size
Inspection Point
TL_UOM
MATERIAL
ACTIVITY
Work center
CONTROL KEY
STANDARD TEXT KEY
INSP. CHAR
MSTR_CHAR
CHA_MASTER_IMPORT MODUS
SMPL_PROCEDURE
SMPL_UNIT
SMPL_QUANT
Are we missing something here ? Is there something else that we should be giving to the BAPI or is there anything missing from the functional perspective ?
All help is greatly appreciated.
Thanks,
Amit
Hi
This message is due to selection of Inspection point completion.
You have selected inspection point say 100 then............
go to operation overview & Check the entry " Quntity ,valuation& comfirmation(Production)" under QM:Inspection point.
Check following.....
This inspection point completion is not possible for task list type Q
Message no. QP259
Diagnosis
A quantity assignment and confirmation are not possible for this task list type:
Procedure
Use one of the possible inspection completion variants:
Valuation
Automatic inspection point valuation
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.