Dear all,

I want configure ECP.

plesae provide me step by step process.

Thanks in advance

Regards

SONAL

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sonal,

ECP Config :-

Step-1: - First Activate one CO-Version in Controlling Area for ECP.

Step-2: - Plan Costing Varient required to Plan costs. Varient "PS06" available in Std SAP for ECP.

Step-3: - Assign Costing varient to Plan Profile.

Step-4: - Assign Plan Profile to Project profile.

Step-5: - one Execution Profile with all required settings as per requirement.

Regards,

Hari

anishpv
Participant
0 Kudos

Hi,

Continuation of what hari has explained

Step 6: Create a Model for ECP.

Regards

Anish PV

Makal
Active Contributor
0 Kudos

Hi,

Continuation of what hari has explained

Step 6: Create a Model for ECP.

Regards

Anish PV

In continuation to what Hari & Anish said, use following T-code for creating costing models:

CKCM - Models for Easy Cost Planning

Former Member
0 Kudos

Pls refer this link, which shows ECP example. For configuration do normal config which you could do for Costing like Costing variant, planning profile etc.

http://help.sap.com/saphelp_46c/helpdata/EN/84/442f38cac1f505e10000009b38f8cf/frameset.htm

Sarang