revenu planning

Former Member
0 Kudos

i want to know about revenue planning

i know, milestone billing plan.

i have also now started learning about other types revenue planning

1. WBS billing plan: on respective WBS elements we plan revenues. till now its ok, nonw how it will be billed? how to proceed? wht are the steps involved???

2. whis is SD billing plan? wht are the steps involved? pls give me the T-code pls

3. WBS billing plan super-seeded SD biling plan ? wht dopes this really mean?

NEED help from all you guys

Regards

surya

Accepted Solutions (0)

Answers (4)

Answers (4)

Makal
Active Contributor
0 Kudos

1. WBS billing plan: on respective WBS elements we plan revenues. till now its ok, nonw how it will be billed? how to proceed? wht are the steps involved???

WBS billing plans are only for planning. WBS billing plans can not generate an actual invoice. They can used for planning before sales document are created.

2. whis is SD billing plan? wht are the steps involved? pls give me the T-code pls

SD billing plan I do not have clear picture how it'll be customized or created. I know couple of things like, document type, item category, account assignment category, requirement type, requirement class must be defined correctly for PS.

Experts can throw more light on this.

WBS billing plan super-seeded SD biling plan ? wht dopes this really mean?

If a WBS billing plan exists, it is used for revenue planning, regardless of the planning on the sales document.

If you have not created a WBS billing plan, the select the option Revenue "From Sales order", in your planning profile.

Then system will automatically plan the revenue based on the total value of the sales order. This will become your planned revenue. As and when invoice is raised to the customer (billing), then actual revenues will flow. And you can see it in any standard report.

I hope this clarifed most, if not all, of your doubts.

Makal
Active Contributor
0 Kudos

Surya

Instead of doing manual revenue planning, you can do automatic revenue planning from Sales order or quotation. Only what you need to do is, in Planning profile, select either "From Quotation" or "From Sales order". What ever is sales order/ quotation value is there, that'll flow in your project as planned revenue.

Whenever they do billing to customer, actual revenue will flow from sales order to your project.

You can see it in the following report:

S_ALR_87013566 - Revenues and Earnings -> Hierarchical -> Actual Contribution Margin

I hope it was helpful.

Former Member
0 Kudos
Former Member
0 Kudos

Hi Surya,

1. WBS Billing Plan :- it is used just to plan revenues but not used for billing.

2. SD Billing Plan :- when assigning WBS as account assignemnt in sale order line item along with delivery dates for that line item, this is nothing but SD billing plan. This gets copied into project on respective wbse as planned revenue.

3. WBS Billing Plan superced SD Billing Plan :- In that above two cases, first priority is give to WBS Billing plan only in PS Revenue Planning. This functionality is available from 4.7 only earlier it gets cumulated as a planned revenue at wbs level.

Hope this clears you..

regards,

Hari Krishna.K

anishpv
Participant
0 Kudos

Hi,

Billing plan provides scheduled dates and amnt(% or bill value) for billing.

pls refer sap help link

[http://help.sap.com/saphelp_47x200/helpdata/en/dd/560674545a11d1a7020000e829fd11/frameset.htm]

Config:

SPRO>SD>Billing-->Billing Plan

these configs can be used in SO >D click line item>Billing plan TAB

Regards

Anish

Edited by: pv on Jun 8, 2009 1:25 PM