on 06-08-2009 6:58 AM
hi,
what are the possible settings that can be maintained for standard text that can maintained during budgeting? where is the settings or config made?
also, is there a report so that I can be able to get an overview of the document texts maintained for a ceratain project?
thanks in advance.
RAm
Hi ,
After executing CJI8 in change layout we can add Text column which shows the budgeet text we put at the time of budgeting
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramesh,
Maintaining text for a Budgeted WBSE is SAP Standard functionality. You can maintain document date, long text and text description.
You can view document text in CJ3B and can be changed either directly in CJ30 or in CJ3A. you can view the same in Budget line items report CJI8
Hope this clears you..
Regards,
Hari Krishna.K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.