reschedule assembly sales order

Former Member
0 Kudos

Hi gurus,

i have a assembly sales order that triger a planned order.

My problem is how to change automatically the eschedule line dates with the ATP availability.

In usual sales orders (without assembly) V_V2 change automatically those dates (schedule lines) based on ATP.

How can i do in this scenario???

What i need is the dates change based on availability of the components of planned order, to know the best date for deliver the sales order.

Can you help me?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hello, friend.

i believe that in SD, the availability takes the production lead times from the material master. the actual availability dates based on the component availability may not update SD ATP logic. the component availability affects PP, though.

i also think that SCM APO may offer the capability for SD to determine availability based on component via GATP/MATP.

regards.