on 06-05-2009 12:48 PM
Hi can i trak this report my client wants to calculate onetime parts delivary percentage "
Ontime parts delivary percentage : Actual arrival date - Requested arrival date
INFORMATION :
DELIVARY NO/ REQUESTED DATE /DELIVARY DATE / DAYS VARIANCE
Many thanks
MvNr
Hi
Guess, you will check this for the sales orders and the report will be for checking the deliveries for the sales orders.
The Requsted delivery date in the sales order is the Requested date for your requirement
The Actual Goods Issue date can be considered for the Delivery date of your requirement
The difference between these two dates will be the variance.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
wants to calculate onetime parts
delivary percentage "
Not sure what does it means. Nevertheless, all delivery related informations are stored in tables LIKP for header related datas and LIPS for item related datas.
Are you recording anywhere the "Days variance" in SAP ??
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can anybody help me on this
Thanks
raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.