Hi experts,

What is the settings required behind sales order for the Assemble-to-order and make-to-order

Thanksin advance,

Anthyodaya.

Edited by: anthyodaya Reddy Nagaram on Jun 5, 2009 10:36 AM

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

ok

Former Member
0 Kudos

Hello

There are no seetings per se for the above requriements in sales order configuration. the production strtergy is linked to sales order through requriemtn types

the requiremtns type is determioned through MRP / group / stratergy group /schedule line assignemtn etc as per sap standard rules

the mrp group / startergy group is entered in material master

you can go to the below t codes for configuration nodes

OVZH

OVZG

OVZI

OVZ8

Hope this helps

Thanks

akasha

Former Member
0 Kudos

Hi

in the normal sales order its creating schedule line automaticalley.

but Assembly oder ATP i am not getting schedule line automaticalley

for verification availability quantity.

Thanksin Advance,

Anthyodaya.

Former Member
0 Kudos

hi reddy,

settings is not needed for the sales order,settings should be maintained for the material master record(material type),and also for the item categoies and the schedule line categories.

thanks

senya

Former Member
0 Kudos

Thanks for the reply,

where can i do setting for the availability quanity for assembly order..

thanks,

NAr

Former Member
0 Kudos

Hi

in the normal sales order its creating schedule line automaticalley.

but Assembly oder ATP i am not getting schedule line automaticalley

for verification availability quantity.