I want to calculate duration ( Setting calculation Key =1 ) based on the setting of workcenter & after giving the work .
Ex :I have a work center (Excavation Machine) which excavate 80M3 sand in 24 hours & same time i had created an activity which have the work of 8000 M3. Now I want to calculate the duration of activity by the setting of calculation key ie calculate duration.
pl help me that what formula i need to maintainin work center for calculating the duration automatically.
Refgards,
Deependra
Hi
You may need to workout some work around or development for this.
You need to maintain work (at activity level) in time units to calculate duration using Calculation key.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.