Hi,
Result Analysis will provide WIP of the Project.
You can use following transactions for calculating wip
KKA2 - Individual Processing
KKAJ - Collective Processing
also you can use tcode CJIF for viewing RA data of the Projects.
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Use T code KKA2 or KKAJ to calculate the WIP of the WBS element.
Thanks
S.Murali