on 04-20-2006 12:51 PM - last edited on 02-04-2024 5:54 AM by postmig_api_4
Hi,
I am loading data from r3 to bw using process chain, all are delta loads and fico data.
process chain scheduled daily at 3.00 am.
Problem is that the data which is extracted into bw is up to 1.00 am only
1-2 and 2-3 (2) hours data is not extracted into bw side.
The client wants reduce the time gap and needs to load all data which acquired into r/3 before to schedule.
Any one can help me in investigation about this.
Thanks in advance.
br,
Narayana
Narayana,
Time stamp is the delta field in your extractor, for your requirement you have enhance you datasource I think.
Thanks
Ram