Hi guys,

I am configuring END to END monitoring in RWB with hel of how to guide. I have created PMI_MONITORING in SXMB_ADM. But i am not able to see all the business systems in my configuration tab page.

Is it required to create the ports using IDX1 in corresponding business systems to connect to integration server?

Regards,

Keith

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos
Former Member
0 Kudos

Hi pratik,

Thanks for u r reply but error i am getting is

No ports that send to the Integration Server could be found for the following ALE logical systems:<br>DSMCLNT200: Unable to log on to system DSM in language en with user XIRWBUSER <br>DR3CLNT200: Unable to log on to system DR3 in language en with user XIRWBUSER <br>DCMCLNT200: Neither the messager server nor the application server can be reached for system DCM <br>

Regards,

Keith.

Former Member
0 Kudos

Hi Keith,

Please can you check step 3.2 End to End Monitoring of How to guide 'How to Monitor Exchange Infrastructure 3.0.pdf'

Also if you are getting error for XIRWBUSER, please can you see if it has all the authorization.

Regards

Vijaya

Former Member
0 Kudos

Hi Vijaya,

I am using same document for configuring end to end monitoring , the user i am using has role SAP_XI_MONITOR.

Regards,

Keith.