GR against APO Scheduling Agreement

Former Member
0 Kudos

We are using APO Scheduling Agreement type LP. (Item Catagory K)

Heuristic creates SNP Scheduling agreement Schedule Line and subsequently, We are able to create releses for these Schedule lines in APO. These releases are seen in MD04 in ECC.

While trying to post GR against these scheduling agreement (on the delivery date) using MIGO in ECC,

Migo does not show up any schedule lines against the Schedule agreement, It throws a message "Document does not contain any selectable items" .

Any one faced a similar issue, Kindly help.

Edited by: Rex Francis on Jun 3, 2009 11:35 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rex,

Please check whether the release profile maintained for Scheduling Aggrement is correct it should be 1:1 in your case since other wise for past days system will sum up all the past requirements.

Path in SPRO APO --> SC Planning --> Collborative Procurement --> Procurement Scheduling Agreement

However here I feel there could be a Badi needs to be implemented Check if "BAdI: Enhancements for the Procurement Scheduling Agreement" could be of some help, I am not very sure.

Thanks

Harsh