on 06-03-2009 6:19 AM
Dear PS & CS Experts
Please can you confirm is there any Open data or Master data to upload in Projects Systems and customer services
Regards
Mujubur
Hi
The master data for PS and CS are as follows:
PS
1. Project No
2. WBS / WBS Element
3. Network
4. Activity
5. BOM
6. Work centre,etc depending upon the business requirement
CS
1. Customer No
2. Address
3. CST No., VAT No, Excise No., etc depending upon the business requirement
Regards
Uddhab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
PS master Data
1. BOM
2. Work Center
3. Investment program and Position
4. Person responsible
5. Applicant no
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In ps following are the master data
WBS Element / Std. WBS Element
Network / Std. Network
Activities
Work Centers
master data can be uploaded by creating project structure manually or if master data is in large amount you can use BDC or LSMW for uploading above master data with help of your abapers.
also ref. below link for use of lsmw.
https://forums.sdn.sap.com/click.jspa?searchID=26922544&messageID=5571982
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.