sepreate Time sheets activities and PS activities

Former Member
0 Kudos

Hi Experts,

Can someone help me on this.

We have wanted to record time against activities which are not similar to project activities.

That is project activities are defined, for reporting and calculating consultants efficiency purposes we wanted to define separate activities, which the user will have choose after selecting the Network and Project activity. How can this be done.

Each of the project activity should be linked to any of the activity which is related to time sheet,

Can this be done to task/task type.

Thanks.

Chandru

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi ,

pls try to use the activity type for activities other than project activities.

Former Member
0 Kudos

Hi

If the CATS is implemented then activity will be captured... otherwise we can always work for seperate acticty for Time sheet and PS if the same are not connected

Uddhab

nitin_patoliya
Active Contributor
0 Kudos

Check the possibility of mapping hte same with Attendance / Abscense type... of Data entry profile. The same is under IMG-> Time Managment..... This will only help you reporting perspose. like as Person A has spend 10 hours on Project activity X , than out of that 10 hours you can find, he has spend 2 hours on traning, 5 hours on consulting, 3 traveling. like as