No Assigned Amount.

Former Member
0 Kudos

Hi!

I have created a project and then created POs using a wbs under this project.

However, no assigned amount is being shown - either in CJ33 or S_ALR_87013542.

Can anybody help?

Regards,

RC.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please check whether the cost elements are created for the GLs that you are using. The T-code is FS00. CO objects are needed to post cost to PS.

Former Member
0 Kudos

Thanks Devdut,

I checked, that part is fine.

Regards,

Riju

Former Member
0 Kudos

Dear Riju,

In T-code OKKP check whether you have ticked Projects & With Commitment Management indiacators for your controlling area. Also make Commitment Management components active. Still if the porblem persists please revert.

Regards,

Gokul

Former Member
0 Kudos

Thanks Gokul,

Issue resolved.

Have a nice day.

Regards,

Riju.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Riju,

Check Commitment Management is active or not in CO Area ?

Check the Availability control status in CJ32 in Extras --> Availability Control --> info, analysis....

If activated, check the Budget Profile for Activation Type and Availability control at what level ? i.e annual ? Overall ? Overall release ? Annual release ??

Still facing problem..revert back !!!

Regards,

Hari

Mrinal_K_Roy
Active Contributor
0 Kudos

Hi,

Check in CJI5 whether commitment appears or not . Is WBS released. You may refer OSS note 178837 also.

Regards,

Mrinal

Former Member
0 Kudos

Hi Hari!

Thanks.

The Availability Control info is as follows:

Availability control is Active

Availability control for: Years

Availability control for: Releases

Availability control in Controlling area currency

The assigned amount is still not showing.

Regards,

Riju.

Former Member
0 Kudos

Thanks Mrinal,

Nothing commitments appearing.

Regards,

Riju