on 06-02-2009 1:25 AM
Hi,experts:
when i create a network with a material componet,the qty is 8
and now the reservation goes to mrp,md03
when this reservation is turn to po.
and the material has been bought back to warehouse
but now still..the qty can be change to 4
is there any method that can restrict qty change in network?
Regards,
Buaalrz
Edited by: buaalrz on Jun 2, 2009 2:26 AM
Hi
Once you complete the all other transaction( PR, PO, GR) confirm the material activity manually, so that the system will not allow you to change the quantity.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.