Hi,experts:

when i create a network with a material componet,the qty is 8

and now the reservation goes to mrp,md03

when this reservation is turn to po.

and the material has been bought back to warehouse

but now still..the qty can be change to 4

is there any method that can restrict qty change in network?

Regards,

Buaalrz

Edited by: buaalrz on Jun 2, 2009 2:26 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Once you complete the all other transaction( PR, PO, GR) confirm the material activity manually, so that the system will not allow you to change the quantity.

Thanks

S.Murali