on 04-19-2006 2:46 PM
Hi all,
How to find the Project and wbs Element System Status.
We can find the system status in the CJ20n transaction but I want the table and field name where it is stored.
Regards
Raghavendra
hi,
For Project definition check this table <b>PROJ</b>
field is <b>PSPNR</b>
Regards
vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the table <b>PRPSS</b> for WBS element.
Regards
vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
Go to cj20n transaction and press f1 and then technical information button on the system status button.
YOu can find the Table and Fields associated.
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.