Dear Friends,

I want solution for rounding off in pricing procedure.Scenario is as below,

I have maintained the base price ZR00 as 1865.00 per TO and ZDLC,a delivery cost as 35.00 per TO.

I have dispatched the material 1.501 TO.

Now system is giving total value as 1900.01.This is because,

1.501 x 1865.00 = 2799.365 as per rounding off concept it is appearing as 2799.37

1.501 x 35.00 = 52.535 as per rounding off concept it is appearing as 52.54

Hence total is 2799.37 + 52.54 = 2851.91.Now total per TO is coming as 2851.91/1.501 = 1900.006.Again as per rounding off concept per TO value is appearing as 1900.01.

My requirement is it should not consider for rounding off.I mean for 1.501 TO it sholud appear as,

Base Price ZR00 as1.501 x 1865.00 = 2799.365

Delivery cost ZDLC as 1.501 x 35.00 = 52.535

So Total = 2799.365 + 52.535 = 2851.900

How to achieve it?

Thanks in advance.

Regards,

Shrikant

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Its a very useful.

eduardo_hinojosa
Active Contributor
0 Kudos

Hi,

Check Note 80183 'Rounding' and related. They will help you.

Regards,

Eduardo