on 05-29-2009 10:28 AM
Hi
Can any body tell me how to do necking in PS like Primivera scheduling.
i mean activity is completed in two or more shifts and in this shift some other activity is proferming.
i want to plan shifts wise activities.
please can any body guide me
thanks
Change ur project calender....customise as per the requirement.................
Regards
surya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you elaborate the solution. because in factory calander working time is not mentioned.
for example I have two activities which have 24 hours. one is completed in two days because the working hour is 8 am to 6 pm. And other is completed in one days because its working time is 24hours.
how to cater this.