Hi,

Any one please guide as to how to migrate from Former budgeting to BCS and also would be of great help what is the advantage of migration f

1 ACCEPTED SOLUTION

former_member184992
Active Contributor
0 Kudos

Hi,

Please check the information available in the following notes:

956356 - Migration from 4.6C FI-FM and former FI-FM releases to BCS

788434 - Allow additive mode in totals migration

Please check also the documentation available in the following menu path:

SPRO -> Public Sector Management -> Funds Management Government -> Budget Control System (BCS) -> Budgeting -> Migration of Former Budgeting to BCS

Please see all the submenus. The first one Overview of Migration Activities will describe all the process and the other ones, the necessary customizing settings. See also the documentation button available in each link.

I hope it helps you

Best Regards,

Vanessa.

View solution in original post

3 REPLIES 3

Former Member
0 Kudos

Sorry the query is not complete earlier.Advantage of migration from former budgeting to BCS.

Regards,

Gokul

0 Kudos

Hi,

BCS is more flexible and client-oriented than former budgeting. It allows you manage several AVC ledgers, define various derivation startegies, better cockpit for budget documents, etc. + you are getting on-going development from SAP for new features, which won't happen anymore in fomer budgeting.

The steps for migration could be seen in help.sap.com; they are quite detailed and could be followed literally.

Regards,

Eli

former_member184992
Active Contributor
0 Kudos

Hi,

Please check the information available in the following notes:

956356 - Migration from 4.6C FI-FM and former FI-FM releases to BCS

788434 - Allow additive mode in totals migration

Please check also the documentation available in the following menu path:

SPRO -> Public Sector Management -> Funds Management Government -> Budget Control System (BCS) -> Budgeting -> Migration of Former Budgeting to BCS

Please see all the submenus. The first one Overview of Migration Activities will describe all the process and the other ones, the necessary customizing settings. See also the documentation button available in each link.

I hope it helps you