Dear Experts,
my cient requremnt is like this they creats the sales order based on customer PO, each Sales Order contains mor than one line item ( that line item BOM and runs MRP at subitem level ). they want assign each line to different cost centers to monitor profitability analysis purpose. how i can map this to PS please suggest me. i want profitability analysis Projectwise and each line item of SO.
and one more doubt can we assign more than one WBS element to one sales order
regards
etr
Hi,
As per me we cant assigne more than one WBS to sales order line item. But u can create level 2 WBS element in project structure and assigne it to sales order line item after ticking it as Billing element.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.