Resposible cost center field should be set blank for WBS >level1.

Former Member
0 Kudos

I want to set " Resp cost center " field blank for WBS element > level1 . i mean to say when i enter the Resp cost center in level 1 WBS element,it should not be copied to the lower level WBS elements automatically.

I know that it can be achieved by Substitution rule.I dont know the steps.Please guide me.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Use Substitution at WBS level as below:

Prerequisite : PROJ-PROFL = 'ABC' AND PRPS-STUFE >= '2'

Substitution: Resp Cost Center - Constant Value - Blank (When you define this step, you will get a lsit of fields on WBS. Select Resp Cctr and then select as constant value and keep it blank)

Assign this substitution in your project profile for automatic substitution, so that when project is saved substitution is carried out.

Thanks

Sarang

Former Member
0 Kudos

Thanks Sarang for your answer.it really helped me a lot.

Answers (2)

Answers (2)

Former Member
0 Kudos

You can also do it thru mass change.

RK

Former Member
0 Kudos

Hi,

If you want to enter cost center only in level 1 WBSE then create the project and enter the cost center at the end in level 1 WBSE.

Muzamil