on 05-28-2009 4:13 PM
Hello ,
we have only a 2 system landscape for our ERP systems.
When I now click on the check button on the maintainance project. I receive an error :
No consolidation system found for DEV-001 (project TEST_CHARM)
No track for project TEST_CHARM with log. system P23/001
Message from function module /TMWFLOW/CHECK_PRJ_CONS: No export system for DEV-001
TMS ( without any client routes)
DEV->PROD
Any suggestions ?
Regards
Even for a two system landscape, you should still have a QA client for unit testing or integration testing in development system. For standard ChaRM to work, you should enable extended transport management. This is prerequisite for ChaRM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Daniel,
we are using CHaRM in various transport landscapes with 2 and up to 5 systems. This is all working fine. Please make sure there is a consolidation transport route from DEV, also all RFC connections from Solution Manager to your Transport Landscape are set up, inlcuding 000 clients.
TMS settings need CTC=1, and Trusted Services in STMS need to be activated.
Other prerequsites are:
- Systems are deined in SMSY
- Transport Domain link between Transport domain controllers
- Logical components defined in SMSY (with correct system roles)
- Lofical component added to SMI project
If this is all fine, please hit button "Shipment Routes" in SOLAR_PROJECT_ADMIN in tab page "System Landscape" => "Systems" You should see all transport routes required for this project.
If this works, you are in a good shape.
Best Regards,
Holger Slomka
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.