on 05-28-2009 2:47 PM
Hello
I am having a batch job for auto settlement of capital projects (starting with C). Just need some input to chk the logic on which I am setting those variants:
1.Create a Variant starting with C* (i.e. all Capital Projects)
2.Use dynamic selection to include all Capital project types (CA,CB,CL etc)
3.Use Selection profile to consider only REL proj and which are not CLSD.
Pls let me know if this is the right approach and is it making sense ? Let me know if I am missing something.
Thanks
Sarang
Hi,
yes this is right you can create a variant like C* and can settle all projects, System will not consider the CLSD projects in this case.
Muzamil