Hi Experts,
Could you please advise what are the steps needed to obtain automatic creation of project from Sales Inquiry?
Thank you in advance!!
Aleksandra
Hi,
1. Create standard WBS CJ91
2.create standard Network CN01
3.Assign material (Finished) to standard network CN08.
SD Config:
1. Create sales document type.
2. Check requirement classes and requirement types take KMPN and 212
Material Master Settings:
3. For material in MM02 material master ,
4.Maintain view MRP3 Strategy group 85 Assembly processing with network/project.
Create Sales order:
Assign material to sales order and while saving it will trigger project.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use Assembly processing to create a project from a Sales order.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You migh have refered this link.. But this is useful one. Few settings in assembly processing are from MM / SD side. Our mates has confimed you most of PS settings.
Please refer this link
http://help.sap.com/erp2005_ehp_04/helpdata/EN/95/1613ab837b11d2b6700000e82d8bd1/frameset.htm
This link is also good one spend sometime on it,
http://help.sap.com/erp2005_ehp_04/helpdata/EN/41/191e9e45fd11d188ff0000e8322f96/frameset.htm
Regards
Nitin P.