Automatic project creation from Sales Document

Former Member
0 Kudos

Hi Experts,

Could you please advise what are the steps needed to obtain automatic creation of project from Sales Inquiry?

Thank you in advance!!

Aleksandra

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

1. Create standard WBS CJ91

2.create standard Network CN01

3.Assign material (Finished) to standard network CN08.

SD Config:

1. Create sales document type.

2. Check requirement classes and requirement types take KMPN and 212

Material Master Settings:

3. For material in MM02 material master ,

4.Maintain view MRP3 Strategy group 85 Assembly processing with network/project.

Create Sales order:

Assign material to sales order and while saving it will trigger project.

Muzamil

Former Member
0 Kudos

Hi,

Use Assembly processing to create a project from a Sales order.

Muzamil

Former Member
0 Kudos

Hi Muzamil,

I know that this is the name of the process, but I don't know the steps. I've created a standard structures and make link to material in CN08. I;ve set up correct Strategy Group and Item Category Group, but it is still not working....

Kind regards, Aleksandra

Former Member
0 Kudos

Hi,

For the material for which you want to create a network, use requirement class 212 or a copy of that to create the network order. Trigger this requirement type from the item category of that material.

nitin_patoliya
Active Contributor
0 Kudos

You migh have refered this link.. But this is useful one. Few settings in assembly processing are from MM / SD side. Our mates has confimed you most of PS settings.

Please refer this link

http://help.sap.com/erp2005_ehp_04/helpdata/EN/95/1613ab837b11d2b6700000e82d8bd1/frameset.htm

This link is also good one spend sometime on it,

http://help.sap.com/erp2005_ehp_04/helpdata/EN/41/191e9e45fd11d188ff0000e8322f96/frameset.htm

Regards

Nitin P.