on 05-28-2009 1:21 PM
Hi,
We have a business model that requires us to change the price of a sales order line item after the item has been partially delivered. Our client is a Steel manufacturer. In Standard SAP (we are on ECC 6) the conditions are grayed out in condition tab of line item after partial delivery.
Did anyone has come across this scenario?
Thanks,
Surya
Dear Surya,
When you do partial / complete delivery, you cant change the price of the sales order item in condition tab.
If at all you want to change the price of the delivered item, you can change the same in Billing document in Condition Tab.
OR
If you want to change the price of the undelivered items. Change the no. Order qty to the actual delivered qty. (Say Out of 50qty, you have delivered 40qty, then make order qty 40) and add one more line item with same material code having remaining undelivered qty. in this case 10. And then change price as per you requirement.
Hope this will help you
Regards,
sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Surya,
in standard SAP it is not possible to change the conditions after a partially delivery.
Because the conditions will be fixed.
Maybe you have the possibility to change KSTEU via userexit.
But this is not recommended from ourside.
I hope that the information are helpful.
regards
Claudia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.