Hi All,
I have a Material of Type FERT. It has a BOM of its own. When I do the product costing of this material for costing variant PPC4, it always explodes the BOM, irrespective of its status of Indicator "With Quantity Structure" in its Material Master.
Note:
1. Costing Variant PPC4 has Indicator "Ignore Product Cost Estimate Without Quantity Structure" set OFF.
2. BOM is exploded irrespective of the Procurement Type.
Pl suggest a way to cost FERT Material without Qty. Structure (no explosing of BOM, instead directly pick the cost from the FERT Mat Master)
Br,
Vasu
Hi,
Hope this link might be of help.
http://help.sap.com/saphelp_erp60_sp/helpdata/EN/7e/cb861c43a311d189ee0000e81ddfac/content.htm
Thanks
Krish.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.