Sales of same material with and without batch

0 Kudos

Hello Experts,

One of my requirement is

To sell single material from same plant

1)with batches and

2)Without batches

Will this be possible in R/3 and how?

Please suggest.

NVS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Nikhil

It Depends on where did you activate the Batch management. If its activated at Plant level, then yes, its possible to maintain the batch for a single material in one plant and no batch in another plant.

But if you activated batch management at material level. then its not possible to have batch assignment in one plant and not in another.

If you have batch activated at material level. what you can do is create a dummy batch in the other plant and the actual batch in the original plant.

Hope this helps..

Thanks

Srini