Hi Gurus,
I need to make the field for "Storage Location" in the "general data" tab of the material component
while planning a material in Project System. I tried in the user interface settings in SPRO, but could not
find it.
Secondly, in order to calculate the overhead rates I need to put "Overhead Key" in each WBS. How can make a setting so that i input the Over head key only in TOP WBSE and the same overhead key is copied to all WBSEs.
Thanks in advance.
Regards,
VDS
For the first one, chekc with user exit. CNEX0009 Material components in network
Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have the same requirement as the first one (make Storage location mandatory),
What was the solution ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi VDS
For second requirement you can try following option:-
Select Project Defination in CJ20N --> Select Mass Change --> select WBS Element tab page --> From available fields select "Overhead Key" --> Select the appropriate Overhead key --> Execute
System will copy same key for all WBS elements under the project defination.
Hope this works for you.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For 2nd question try Substitution.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.