Is someone know if an extractor of the Business Content give the following date : planned delivery date and the effective delivery date.
For the purchase, I need to check what are the commands in late. I need to check if the planned delivery date is overreached and if the effective delivery date is empty.
I have no knowledge on R/3, so I don't know where to search and I don't succeed to find a Business content's extractor containing this 2 information
Hi,
You can start by looking at the Metadata Repository.
Cheers,
Kedar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Christophe,
see if it helps -
http://help.sap.com/saphelp_bw33/helpdata/en/28/f3b55245b860499d619c475c57ff20/content.htm
regards
Vikash
User | Count |
---|---|
83 | |
10 | |
10 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.