Division cannot be carried out because divisor is zero - EA00

Former Member
0 Kudos

hi,

While doing EA00 transaction following error occurs:

During billing simulation, a termination occurs with message AJ020 (Division cannot be carried out because divisor is zero) or AJ097 (Unexpected termination in variant &1 in schema &2)

I gone through the note 402960

Note says, The termination can occur, for example, when

1) you choose pushbutton "Overall check" on the move-in screen,

2) the move-out date of a contract is equal to the move-in date,

3) one-day time slices are to be billed

The overall check in the move-in is called with a one-day time slice.That is, the move-in date is selected as the to-date.

Solution

Correct your billing schema.

Use IF nestings to make sure that only schema steps, which can also be executed with zero values, are executed. For example,a division by zero should be avoided.

My problem is I did not understood what exactly has to change in schema.pls help???

Regards,

Chetan

2 REPLIES 2

Former Member
0 Kudos

Can you mention the variant Program you are using on this step. The Divisor operand value seems to have become zero. You may need to check how this operand value is being populated.

Former Member
0 Kudos

closing the issue.