on 05-26-2009 7:34 PM
hi friends
i want a scenario, that an activity will not start before completion of an activity
i don't want anyone to confirm or input to a 2nd activity till the first activity is completed.........
is it so possible??? if so how????
Regards
Surya
Y ou can does like Finish to start relationship between two activities.
Option 1 :
You can lock the master dat of the second activity, vis system status. till the time your complete the first activity.
Options 2 :
Manitain constraints on First activity mujst finish on 28.05.2009.
Second activity maintain constraint cannot start before 29.05.2009.
Activate user status ( Forbid Confimr Transaction ) for the second activity till the time first activity gets confirmed,
Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can archive this either by using User status or Constraints.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
maintain a FS relationship between the two activities and put a constraint 'Cannot start before' for the second activity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Surya,
Do not release the second activity till first finish or till you are comfortable.
regds,
Deependra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.