on 05-26-2009 5:44 PM
Hi Experts,
I have one network with two activities having FS relationship with duration for ex.10 & 20Days.
Activity 1: ES = 01-01-2009 & EF = 10-01-2009 (Date -Month - Year format)
Activity 2: ES = 11-01-2009 & EF = 30-01-2009
I havedone the following settings:
1) Adjust Basic Dates
2) Automatic Scheduling
3) In confirmation parameters - Propose dates
Now I had done the partial confirmation of activity 1 with actual start 03-01-2009 & Actual Finish 11-01-2009 & forcast duration 2 days
Now when i save the NW or Project but system dose not do the automatic scheduling Earliest dates remain same .For this I have to do manually
Can some one help so that the system schedule automatically & the result would be as
Activity 1: ES = 03-01-2009 & EF = 13-01-2009
Activity 2: ES = 14-01-2009 & EF = 03-02-2009
Regards,
Deependra
Hi Deepender,
You have planned only nornal duration for both activities. even though automatic scheduling is selected for network system will not consider actual date into schedule dates. same you confirm partially with capacities in your activity and observe the changes in your schedule dates after partial confirmation.
Regards,
hari krishna.K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The ES and EF dates are the dates for planning only. Scheduling is done for the planning purpose only.
Once you do the actual / partial confirmation of the activity, the difference between your planned visa-vis your actual dates will help you to understand your planned credentials.
Regards,
Uddhab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Are you using WBS scheduling or network scheduling? For network scheduling goto OPU6, check for required plant and network order type and check Adjust Basic Dates key ' ' and Automatic Scheduling.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deependra
Check whether
'scheduling' is flagged in the control key of the operation.
Regards,
Mrinal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.