on 05-26-2009 12:26 PM
Hi Gurus,
Is there any report which include different cost i.e Budgeted value, actual value, actual revenue for projects (all wbs) executed in perticular time period.
If i want to customize report which table and field required for the same pls provide me details for that.
Regards
VJ
Edited by: vrunda on May 26, 2009 1:29 PM
You can also create a custom line item report similar to CJI3 and CJI8 with required columns like Budget, Actual cost, Actual Revenue.... In the slection screen you can select multiple projects or WBSE or NWA, all these for a given date range. The output would be for the selected date range and gives you all objects which have data in the specified date range.
Regards
RK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can use CJE0 which will give you a consolidated list of all the reports in PS
Regards,
Uddhab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can also create a Hierarchy report using CJE4 and CJE1. Here you can include any column you want based on certain characteristics predefined. You can also use Business Txn as one of the characteristic and get the data. You can select drill down options based on Period/Year, Companycode etc and you can get the values on period basis when you drill down the report.
Best Regards..
RK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In CNS41 use multiple selection to select all projects
in the intial screnn of the report choose field to set the budget,actual and revenue
this will give values for the all projects
select the last object of the any project and then double click on filter
again choose fileds for the respective fields then from menu bar goto-->periodic breakdown
will give over all summary of the individual project object accross the period.
regards
pv
Hi,
You can also use CNS41 report to get Budet, cost and revenue for the WBS.
BR,
Morshed Alam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
check following reports
S_ALR_87013557 - Budget/Actual/Variance
S_ALR_87013564 - Plan Revenue/Actual Revanue/Variance
CJI3 - Actual Costs/Revenues
tables
RPSCO Project Info Database (cost, revenues)
BPGE Budget: Overall Values
BPJA Budget: Annual Values
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
for Budget CJI8 for actual cost/rev CJI3 the values u will get in RPSCO table.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.