hi all, i tried to do settlement through cj8g.i specified the settlement period.but i found that projects not falling in that settlement period were also picked up,?why?how do we specify the search criteria for cj8g?
Hi,
CJ8G - Single Functions -> Settlement -> Collective Processing, this transaction is used for collective settlement of projects.
If you have multiple projects ( for ex. 50 projects ) & you want to carry out perodic or final settlement for all 50 projects at a time, it can be possible through CJ8G by creating selection variant.
CJ88 - Individual Processing, this transaction is used for individual settlement of projects.
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
While creating variant you specify the projects which you want to settle for this period and then run the settlement. So you can avoid the other projects inclusion in that.
For the next period you change the selection of projects for the same variant .
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chirald,
While creating the selection varient, system consider all the projects (range) you mentioned in the varient, but while creating the selection varient, you can select the selection type and E/I indicators.
But finally system will consider all projects for settlement as per the given Period and selected projects in that varient. So, what ever the projects you don't want to consider for settlement, you should exclude those projects in that varient.
Regards,
Hari Krishna.K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.