Dear PS experts,
Our clinet is doing frequent changes in scheduling of the project .
Path CJ20N >Edit>dates---> Schedule(The scheduling carried out at Project level)
1)Let me know where changes related to Reschedulings are saved (table )
it should contain a) Last Schedule run by whom and when?
Regards
Project Team1
Hi ,
If u have maintained change documents option active in ur project profile ( OPSA status management tab Change docs ticked ) then u can see the changes in CN60 transaction.
If u see this report u can get all the changes done on ur project if during schedulling date changes r done then u can see it with date, time n who is the user done it.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
use tcode: cj20
in menu goto: extras>log>scheduling.
check if this helps!
regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.