Dear All,
WE are transferring Stocks between Manufacturing plant/Depot to our portplant in export sales.our client wants that if they do PGI in the Stocktransfer delivery it should be updated in the Port plant unrestricted stock.
Please suggest me which movement type has to be used
or Shall i use Movement type 1 step in schedule line category.,if i use that which movement type i have to use in
1)movement type
2)movement type 1 step.
REgards
Ramesh
ok thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Standard solution is available for this in standard itself
In VOV6 the schedule line category NN should have
Movement type as 641
Movement type 1 step as 647
This is the standard settings for intra company
One step mean there wont be any stocks in transit
For intercompany In VOV6 the schedule line category NC should have
Movement type as 643
Movement type 1 step as 645
If you take these movement types there wont be any problem
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.