on 05-26-2009 4:38 AM
Dear ps experts,
I have a requirement of stock item goods issue to project stock (special stock) "Q" through Network.
from project stock, as per new business process, I will have to do pgi against sales order for same stock item from project stock "Q"
Example:
In network - ext- processing, I have 3 materials to be procured through pr-po process and after GR, the same materials are shown in project stock (Q). In the same network, I have one stock item, which is to be issued to project stock "Q"
Please help,
regards
Sri hari
Hi,
1You can use CNS0 (Delivery from projects).It depends on the reservation created in project.Click CNS0,enter the required details like Sales org,sales area etc and save the delivery.After go to VL02N and click PGI after picking.
2.Use MB1A and with ref to reservation post the document.
The Movement type will be 281 Q.
Thanks
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.